NZ IFRIC 12

Service Concession Arrangements

Mandatory Date:
{{ matches.count }} matches for: {{ matches.query }}

Statement of Authority

New Zealand Equivalent to IFRIC Interpretation 12 Service Concession Arrangements (NZ IFRIC 12)

Issued March 2007 and incorporates amendments to 31 January 2019

This Interpretation was issued by the New Zealand Accounting Standards Board of the External Reporting Board pursuant to section 24(1)(a) of the Financial Reporting Act 1993.

This Interpretation is a Regulation for the purposes of the Regulations (Disallowance) Act 1989.

COPYRIGHT

© External Reporting Board (XRB) 2011

This XRB standard contains International Financial Reporting Standards (IFRS®) Foundation copyright material. Reproduction within New Zealand in unaltered form (retaining this notice) is permitted for personal and non-commercial use subject to the inclusion of an acknowledgement of the source.

Requests and enquiries concerning reproduction and rights for commercial purposes within New Zealand should be addressed to the Chief Executive, External Reporting Board at the following email address: enquiries@xrb.govt.nz and the IFRS Foundation at the following email address: permissions@ifrs.org.

All existing rights (including copyrights) in this material outside of New Zealand are reserved by the IFRS Foundation. Further information and requests for authorisation to reproduce for commercial purposes outside New Zealand should be addressed to the IFRS Foundation.

ISBN 978-1-877430-85-5

Copyright

IFRS Standards are issued by the International Accounting Standards Board

Columbus Building, 7 Westferry Circus, Canary Wharf, London, E14 4HD, United Kingdom. Tel: +44 (0)20 7246 6410

Email: info@ifrs.org Web: www.ifrs.org

Copyright © International Financial Reporting Standards Foundation All rights reserved. Reproduced and distributed by the External Reporting Board with the permission of the IFRS Foundation. This English language version of the IFRS Standards is the copyright of the IFRS Foundation.

1. The IFRS Foundation grants users of the English language version of IFRS Standards (Users) the permission to reproduce the IFRS Standards for

  1. the User’s Professional Use, or

  2. private study and education

Professional Use: means use of the English language version of the IFRS Standards in the User’s professional capacity in connection with the business of providing accounting services for the purpose of application of IFRS Standards for preparation of financial statements and/or financial statement analysis to the User’s clients or to the business in which the User is engaged as an accountant.

For the avoidance of doubt, the abovementioned usage does not include any kind of activities that make (commercial) use of the IFRS Standards other than direct or indirect application of IFRS Standards, such as but not limited to commercial seminars, conferences, commercial training or similar events.

2. For any application that falls outside Professional Use, Users shall be obliged to contact the IFRS Foundation for a separate individual licence under terms and conditions to be mutually agreed.

3. Except as otherwise expressly permitted in this notice, Users shall not, without prior written permission of the Foundation have the right to license, sublicense, transmit, transfer, sell, rent, or otherwise distribute any portion of the IFRS Standards to third parties in any form or by any means, whether electronic, mechanical or otherwise either currently known or yet to be invented.

4. Users are not permitted to modify or make alterations, additions or amendments to or create any derivative works, save as otherwise expressly permitted in this notice.

5. Commercial reproduction and use rights are strictly prohibited. For further information please contact the IFRS Foundation at permissions@ifrs.org.

The authoritative text of IFRS Standards is that issued by the International Accounting Standards Board in the English language. Copies may be obtained from the IFRS Foundation’s Publications Department.

Please address publication and copyright matters in English to:

IFRS Foundation Publications Department

Columbus Building, 7 Westferry Circus, Canary Wharf, London, E14 4HD, United Kingdom. Tel: +44 (0)20 7332 2730 Fax: +44 (0)20 7332 2749

Email: publications@ifrs.org Web: www.ifrs.org

Trade Marks

IFRS_Logo_rgb

The IFRS Foundation logo, the IASB logo, the IFRS for SMEs logo, the “Hexagon Device”, “IFRS Foundation”, “eIFRS”, “IAS”, “IASB”, “IFRS for SMEs”, “IASs”, “IFRS”, “IFRSs”, “International Accounting Standards” and “International Financial Reporting Standards”, “IFRIC” and “SIC” are Trade Marks of the IFRS Foundation.

Disclaimer

The authoritative text of the IFRS Standards is reproduced and distributed by the External Reporting Board in respect of their application in New Zealand. The International Accounting Standards Board, the Foundation, the authors and the publishers do not accept responsibility for loss caused to any person who acts or refrains from acting in reliance on the material in this publication, whether such loss is caused by negligence or otherwise.

How to read this Standard

New Zealand Equivalent to IFRIC Interpretation 12 Service Concession Arrangements (NZ IFRIC 12) is set out in paragraphs 1–30 and Appendices A and B.

NZ IFRIC 12 is accompanied by IFRIC Information Notes, IFRIC Illustrative Examples and an IFRIC Basis for Conclusions. NZ IFRIC 12 should be read in the context of the IFRIC’s Basis for Conclusions on IFRIC 12 and the Illustrative Examples for IFRIC 12.

Any New Zealand additional material is shown with either “NZ” or “RDR” preceding the paragraph number.

Reduced Disclosure Regime

Tier 2 for-profit entities must comply with all the provisions in NZ IFRIC 12.

References

  • NZ Framework for the Preparation and Presentation of Financial Statements1

  • NZ IFRS 1 First-time Adoption of New Zealand Equivalents to International Financial Reporting Standards

  • NZ IFRS 7 Financial Instruments: Disclosures

  • NZ IFRS 9 Financial Instruments

  • NZ IFRS 15 Revenue from Contracts with Customers

  • NZ IFRS 16 Leases

  • NZ IAS 8 Accounting Policies, Changes in Accounting Estimates and Errors

  • NZ IAS 16 Property, Plant and Equipment

  • NZ IAS 20 Accounting for Government Grants and Disclosure of Government Assistance

  • NZ IAS 23 Borrowing Costs

  • NZ IAS 32 Financial Instruments: Presentation

  • NZ IAS 36 Impairment of Assets

  • NZ IAS 37 Provisions, Contingent Liabilities and Contingent Assets

  • NZ IAS 38 Intangible Assets

  • NZ SIC-29 Service Concession Arrangements: Disclosures2

1 In many countries, infrastructure for public services—such as roads, bridges, tunnels, prisons, hospitals, airports, water distribution facilities, energy supply and telecommunication networks—has traditionally been constructed, operated and maintained by the public sector and financed through public budget appropriation.

2 In some countries, governments have introduced contractual service arrangements to attract private sector participation in the development, financing, operation and maintenance of such infrastructure. The infrastructure may already exist, or may be constructed during the period of the service arrangement. An arrangement within the scope of this Interpretation typically involves a private sector entity (an operator) constructing the infrastructure used to provide the public service or upgrading it (for example, by increasing its capacity) and operating and maintaining that infrastructure for a specified period of time. The operator is paid for its services over the period of the arrangement. The arrangement is governed by a contract that sets out performance standards, mechanisms for adjusting prices, and arrangements for arbitrating disputes. Such an arrangement is often described as a ‘build-operate-transfer’, a ‘rehabilitate-operate-transfer’ or a ‘public- to-private’ service concession arrangement.

3 A feature of these service arrangements is the public service nature of the obligation undertaken by the operator. Public policy is for the services related to the infrastructure to be provided to the public, irrespective of the identity of the party that operates the services. The service arrangement contractually obliges the operator to provide the services to the public on behalf of the public sector entity. Other common features are:

  1. the party that grants the service arrangement (the grantor) is a public sector entity, including a governmental body, or a private sector entity to which the responsibility for the service has been devolved.

  2. the operator is responsible for at least some of the management of the infrastructure and related services and does not merely act as an agent on behalf of the grantor.

  3. the contract sets the initial prices to be levied by the operator and regulates price revisions over the period of the service arrangement.

  4. the operator is obliged to hand over the infrastructure to the grantor in a specified condition at the end of the period of the arrangement, for little or no incremental consideration, irrespective of which party initially financed it.

 

1 The conceptual framework that was in effect when the IASB developed IFRIC 12 was the IASC’s Framework for the Preparation and Presentation of Financial Statements, adopted by the IASB in 2001. IFRIC 12 refers to that framework. The equivalent New Zealand pronouncement was the New Zealand Equivalent to the IASB Framework for the Preparation and Presentation of Financial Statements which was replaced by the New Zealand Equivalent to the IASB Conceptual Framework for Financial Reporting 2010.

2 The title of NZ SIC-29, formerly Disclosure–Service Concession Arrangements, was amended by NZ IFRIC 12.

NZ3.1 This Interpretation applies to Tier 1 and Tier 2 for-profit entities.

4 This Interpretation gives guidance on the accounting by operators for public-to-private service concession arrangements.

5 This Interpretation applies to public-to-private service concession arrangements if:

  1. the grantor controls or regulates what services the operator must provide with the infrastructure, to whom it must provide them, and at what price; and

  2. the grantor controls—through ownership, beneficial entitlement or otherwise—any significant residual interest in the infrastructure at the end of the term of the arrangement.

6 Infrastructure used in a public-to-private service concession arrangement for its entire useful life (whole of life assets) is within the scope of this Interpretation if the conditions in paragraph 5(a) are met. Paragraphs AG1-AG8 provide guidance on determining whether, and to what extent, public-to-private service concession arrangements are within the scope of this Interpretation.

7 This Interpretation applies to both:

  1. infrastructure that the operator constructs or acquires from a third party for the purpose of the service arrangement; and

  2. existing infrastructure to which the grantor gives the operator access for the purpose of the service arrangement.

8 This Interpretation does not specify the accounting for infrastructure that was held and recognised as property, plant and equipment by the operator before entering the service arrangement. The derecognition requirements of NZ IFRS (set out in NZ IAS 16) apply to such infrastructure.

9 This Interpretation does not specify the accounting by grantors.

10 This Interpretation sets out general principles on recognising and measuring the obligations and related rights in service concession arrangements. Requirements for disclosing information about service concession arrangements are in NZ SIC-29. The issues addressed in this Interpretation are:

  1. treatment of the operator’s rights over the infrastructure;

  2. recognition and measurement of arrangement consideration;

  3. construction or upgrade services;

  4. operation services;

  5. borrowing costs;

  6. subsequent accounting treatment of a financial asset and an intangible asset; and

  7. items provided to the operator by the grantor.

Treatment of the operator’s rights over the infrastructure

11 Infrastructure within the scope of this Interpretation shall not be recognised as property, plant and equipment of the operator because the contractual service arrangement does not convey the right to control the use of the public service infrastructure to the operator. The operator has access to operate the infrastructure to provide the public service on behalf of the grantor in accordance with the terms specified in the contract.

Recognition and measurement of arrangement consideration

12 Under the terms of contractual arrangements within the scope of this Interpretation, the operator acts as a service provider. The operator constructs or upgrades infrastructure (construction or upgrade services) used to provide a public service and operates and maintains that infrastructure (operation services) for a specified period of time.

13 The operator shall recognise and measure revenue in accordance with NZ IFRS 15 for the services it performs. The nature of the consideration determines its subsequent accounting treatment. The subsequent accounting for consideration received as a financial asset and as an intangible asset is detailed in paragraphs 23–26 below.

Construction or upgrade services

14 The operator shall account for revenue and costs relating to construction or upgrade services in accordance with NZ IFRS 15.

Consideration given by the grantor to the operator

15 If the operator provides construction or upgrade services the consideration received or receivable by the operator shall be recognised in accordance with NZ IFRS 15. The consideration may be rights to:

  1. a financial asset, or

  2. an intangible asset.

16 The operator shall recognise a financial asset to the extent that it has an unconditional contractual right to receive cash or another financial asset from or at the direction of the grantor for the construction services; the grantor has little, if any, discretion to avoid payment, usually because the agreement is enforceable by law. The operator has an unconditional right to receive cash if the grantor contractually guarantees to pay the operator (a) specified or determinable amounts or (b) the shortfall, if any, between amounts received from users of the public service and specified or determinable amounts, even if payment is contingent on the operator ensuring that the infrastructure meets specified quality or efficiency requirements.

17 The operator shall recognise an intangible asset to the extent that it receives a right (a licence) to charge users of the public service. A right to charge users of the public service is not an unconditional right to receive cash because the amounts are contingent on the extent that the public uses the service.

18 If the operator is paid for the construction services partly by a financial asset and partly by an intangible asset it is necessary to account separately for each component of the operator’s consideration. The consideration received or receivable for both components shall be recognised initially in accordance with NZ IFRS 15.

19 The nature of the consideration given by the grantor to the operator shall be determined by reference to the contract terms and, when it exists, relevant contract law. The nature of the consideration determines the subsequent accounting as described in paragraphs 23–26. However, both types of consideration are classified as a contract asset during the construction or upgrade period in accordance with NZ IFRS 15.

Operation services

20 The operator shall account for operation services in accordance with NZ IFRS 15.

Contractual obligations to restore the infrastructure to a specified level of serviceability

21 The operator may have contractual obligations it must fulfil as a condition of its licence (a) to maintain the infrastructure to a specified level of serviceability or (b) to restore the infrastructure to a specified condition before it is handed over to the grantor at the end of the service arrangement. These contractual obligations to maintain or restore infrastructure, except for any upgrade element (see paragraph 14), shall be recognised and measured in accordance with NZ IAS 37, ie at the best estimate of the expenditure that would be required to settle the present obligation at the end of the reporting period.

Borrowing costs incurred by the operator

22 In accordance with NZ IAS 23, borrowing costs attributable to the arrangement shall be recognised as an expense in the period in which they are incurred unless the operator has a contractual right to receive an intangible asset (a right to charge users of the public service). In this case borrowing costs attributable to the arrangement shall be capitalised during the construction phase of the arrangement in accordance with that Standard.

Financial asset

23 NZ IAS 32 and NZ IFRSs 7 and 9 apply to the financial asset recognised under paragraphs 16 and 18.

24 The amount due from or at the direction of the grantor is accounted for in accordance with NZ IFRS 9 as measured at:

  1. amortised cost;

  2. fair value through other comprehensive income; or

  3. fair value through profit or loss.

25 If the amount due from the grantor is measured at amortised cost or fair value through other comprehensive income, NZ IFRS 9 requires interest calculated using the effective interest method to be recognised in profit or loss.

Intangible asset

26 NZ IAS 38 applies to the intangible asset recognised in accordance with paragraphs 17 and 18. Paragraphs 45–47 of NZ IAS 38 provide guidance on measuring intangible assets acquired in exchange for a non-monetary asset or assets or a combination of monetary and non-monetary assets.

Items provided to the operator by the grantor

27 In accordance with paragraph 11, infrastructure items to which the operator is given access by the grantor for the purposes of the service arrangement are not recognised as property, plant and equipment of the operator. The grantor may also provide other items to the operator that the operator can keep or deal with as it wishes. If such assets form part of the consideration payable by the grantor for the services, they are not government grants as defined in NZ IAS 20. Instead, they are accounted for as part of the transaction price as defined in NZ IFRS 15.

28 An entity shall apply NZ IFRIC 12 in its annual financial statements for periods beginning on or after 1 January 2008. Earlier application is permitted only when an entity complies, or has complied, with NZ IFRS 1 First-Time Adoption of New Zealand Equivalents to International Financial Reporting Standards in its annual financial statements for a period beginning on or after 1 January 2005. If an entity applies this NZ IFRIC in its financial statements for a period before 1 January 2008, it shall disclose that fact.

NZ28.1 Framework: Tier 1 and Tier 2 For-profit Entities, issued in November 2012, amended extant NZ IFRSs by deleting any public benefit entity paragraphs, deleting any differential reporting concessions, adding scope paragraphs for Tier 1 and Tier 2 for-profit entities and adding disclosure concessions for Tier 2 entities. It made no changes to the requirements for Tier 1 entities. A Tier 2 entity may elect to apply the disclosure concessions for annual periods beginning on or after 1 December 2012. Early application is permitted.

28A–28C [Deleted by IASB]

28D NZ IFRS 15 Revenue from Contracts with Customers, issued in July 2014, amended the ‘References’ section, the table in Information note 2 and paragraphs 13–15, 18–20 and 27. An entity shall apply those amendments when it applies NZ IFRS 15.

28E NZ IFRS 9, as issued in September 2014, amended paragraphs 23–25 and deleted paragraphs 28A–28C. An entity shall apply those amendments when it applies NZ IFRS 9.

28F NZ IFRS 16, issued in February 2016, amended paragraph AG8. An entity shall apply that amendment when it applies NZ IFRS 16.

29 Subject to paragraph 30, changes in accounting policies are accounted for in accordance with NZ IAS 8, ie retrospectively.

30 If, for any particular service arrangement, it is impracticable for an operator to apply this Interpretation retrospectively at the start of the earliest period presented, it shall:

  1. recognise financial assets and intangible assets that existed at the start of the earliest period presented;

  2. use the previous carrying amounts of those financial and intangible assets (however previously classified) as their carrying amounts as at that date; and

  3. test financial and intangible assets recognised at that date for impairment, unless this is not practicable, in which case the amounts shall be tested for impairment as at the start of the current period.

[The IFRIC Information Notes accompany but do not form part of NZ IFRIC 12.]
[These examples accompany but do not form part of NZ IFRIC 12.]

BC1–BC77 [Paragraphs BC1–BC77 do not form part of NZ IFRIC 12.]

This appendix is an integral part of the Interpretation.

Scope (paragraph 5)

AG1 Paragraph 5 of this Interpretation specifies that infrastructure is within the scope of the Interpretation when the following conditions apply:

  1. the grantor controls or regulates what services the operator must provide with the infrastructure, to whom it must provide them, and at what price; and

  2. the grantor controls—through ownership, beneficial entitlement or otherwise—any significant residual interest in the infrastructure at the end of the term of the arrangement.

AG2 The control or regulation referred to in condition (a) could be by contract or otherwise (such as through a regulator), and includes circumstances in which the grantor buys all of the output as well as those in which some or all of the output is bought by other users. In applying this condition, the grantor and any related parties shall be considered together. If the grantor is a public sector entity, the public sector as a whole, together with any regulators acting in the public interest, shall be regarded as related to the grantor for the purposes of this Interpretation.

AG3 For the purpose of condition (a), the grantor does not need to have complete control of the price: it is sufficient for the price to be regulated by the grantor, contract or regulator, for example by a capping mechanism. However, the condition shall be applied to the substance of the agreement. Non-substantive features, such as a cap that will apply only in remote circumstances, shall be ignored. Conversely, if for example, a contract purports to give the operator freedom to set prices, but any excess profit is returned to the grantor, the operator’s return is capped and the price element of the control test is met.

AG4 For the purpose of condition (b), the grantor’s control over any significant residual interest should both restrict the operator’s practical ability to sell or pledge the infrastructure and give the grantor a continuing right of use throughout the period of the arrangement. The residual interest in the infrastructure is the estimated current value of the infrastructure as if it were already of the age and in the condition expected at the end of the period of the arrangement.

AG5 Control should be distinguished from management. If the grantor retains both the degree of control described in paragraph 5(a) and any significant residual interest in the infrastructure, the operator is only managing the infrastructure on the grantor’s behalf—even though, in many cases, it may have wide managerial discretion.

AG6 Conditions (a) and (b) together identify when the infrastructure, including any replacements required (see paragraph 21), is controlled by the grantor for the whole of its economic life. For example, if the operator has to replace part of an item of infrastructure during the period of the arrangement (eg the top layer of a road or the roof of a building), the item of infrastructure shall be considered as a whole. Thus condition (b) is met for the whole of the infrastructure, including the part that is replaced, if the grantor controls any significant residual interest in the final replacement of that part.

AG7 Sometimes the use of infrastructure is partly regulated in the manner described in paragraph 5(a) and partly unregulated. However, these arrangements take a variety of forms:

  1. any infrastructure that is physically separable and capable of being operated independently and meets the definition of a cash-generating unit as defined in NZ IAS 36 shall be analysed separately if it is used wholly for unregulated purposes. For example, this might apply to a private wing of a hospital, where the remainder of the hospital is used by the grantor to treat public patients.

  2. when purely ancillary activities (such as a hospital shop) are unregulated, the control tests shall be applied as if those services did not exist, because in cases in which the grantor controls the services in the manner described in paragraph 5, the existence of ancillary activities does not detract from the grantor’s control of the infrastructure.

AG8 The operator may have a right to use the separable infrastructure described in paragraph AG7(a), or the facilities used to provide ancillary unregulated services described in paragraph AG7(b). In either case, there may in substance be a lease from the grantor to the operator; if so, it shall be accounted for in accordance with NZ IFRS 16.

Amendments to NZ IFRS 1 and to other Interpretations

The amendments in this appendix shall be applied for annual periods beginning on or after 1 January 2008. If an entity applies this Interpretation for an earlier period, these amendments shall be applied for that earlier period.

* *****

The amendments contained in this appendix when this Interpretation was issued in 2007 have been incorporated into the relevant pronouncements.

Table of Pronouncements – NZ IFRIC 12 Service Concession Arrangements

This table lists the pronouncements establishing and substantially amending NZ IFRIC 12. The table is based on amendments approved as at 31 January 2019.

Pronouncements

Date approved

Early operative date

Effective date (annual reporting periods… on or after …)

NZ IFRIC 12 Service Concession Arrangements

Mar 2007

Early application permitted

1 Jan 2008

NZ IAS 23 Borrowing Costs (revised 2007)

July 2007

Early application permitted

1 Jan 2009

NZ IFRS 9 Financial Instruments (2009)

Nov 2009

Early application permitted

1 Jan 20131

NZ IFRS 9 Financial Instruments (2010)

Nov 2010

Early application permitted

1 Jan 20132

Framework: Tier 1 and Tier 2 For-profit Entities3

Nov 2012

Early application permitted

1 Dec 2012

NZ IFRS 9 Financial Instruments (2013) (Hedge Accounting and Amendments to NZ IFRS 9, NZ IFRS 7 and NZ IAS 39)

Dec 2013

Early application permitted

1 Jan 20174

NZ IFRS 15 Revenue from Contracts with Customers

July 2014

Early application permitted

1 Jan 20185

NZ IFRS 9 Financial Instruments (2014)

Sept 2014

Early application permitted

1 Jan 2018

NZ IFRS 16 Leases

Feb 2016

Early application permitted

1 Jan 2019

Amendments to References to the Conceptual Framework in NZ IFRS

May 2018

Early application permitted

1 Jan 2020

Table of Amended Paragraphs in NZ IFRIC 12

Paragraph affected

How affected

By … [date]

References

Amended

NZ IFRS 9 (2009) [Nov 2009], NZ IFRS 9 (2010) [Nov 2010],

NZ IFRS 9 (2013) [Dec 2013] and NZ IFRS 9 (2014) [Sept 2014]

References

Amended

NZ IFRS 15 [July 2014]

References

Amended

NZ IFRS 16 [Feb 2016]

References

Amended

Amendments to References to the Conceptual Framework in NZ IFRS [May 2018]

Paragraphs 13–15

Amended

NZ IFRS 15 [July 2014]

Paragraphs 18–20

Amended

NZ IFRS 15 [July 2014]

Paragraph 22

Amended

NZ IAS 23 [July 2007]

Paragraphs 23–25

Amended

NZ IFRS 9 (2009) [Nov 2009], NZ IFRS 9 (2010) [Nov 2010],

NZ IFRS 9 (2013) [Dec 2013] and NZ IFRS 9 (2014) [Sept 2014]

Paragraph 27

Amended

NZ IFRS 15 [July 2014]

Paragraph NZ 28.1

Added

Framework: Tier 1 and Tier 2 For-profit Entities [Nov 2012]

Paragraph 28A

Added

NZ IFRS 9 (2009) [Nov 2009]

Paragraph 28A

Deleted

NZ IFRS 9 (2010) [Nov 2010] and NZ IFRS 9 (2014) [Sept 2014]

Paragraph 28B

Added

NZ IFRS 9 (2010) [Nov 2010]

Paragraph 28B

Deleted

NZ IFRS 9 (2013) [Dec 2013] and NZ IFRS 9 (2014) [Sept 2014]

Paragraph 28C

Added

NZ IFRS 9 (2013) [Dec 2013]

Paragraph 28C

Deleted

NZ IFRS 9 (2014) [Sept 2014]

Paragraph 28D

Added

NZ IFRS 15 [July 2014]

Paragraph 28E

Added

NZ IFRS 9 (2014) [Sept 2014]

Paragraph 28F

Added

NZ IFRS 16 [Feb 2016]

Paragraph AG8

Amended

NZ IFRS 16 [Feb 2016]

1Superseded by NZ IFRS 9 Financial Instruments (2014). NZ IFRS 9 (2014) restricted early application of earlier versions of NZ IFRS 9.

2Superseded by NZ IFRS 9 Financial Instruments (2014). NZ IFRS 9 (2014) restricted early application of earlier versions of NZ IFRS 9.

3 This pronouncement amended extant NZ IFRSs by (i) deleting any public benefit entity paragraphs, (ii) deleting any differential reporting paragraphs, (iii) adding scope paragraphs for Tier 1 and Tier 2 for-profit entities, and (iv) adding RDR disclosure concessions.

4Superseded by NZ IFRS 9 Financial Instruments (2014). NZ IFRS 9 (2014) restricted early application of earlier versions of NZ IFRS 9.

5Effective date of NZ IFRS 15, issued in November 2015, deferred the mandatory effective date of NZ IFRS 15 from annual reporting periods beginning on or after 1 January 2017 to annual reporting periods beginning on or after 1 January 2018.